Gona Sivanaga Babu has 6 AP-RERA registered projects across Guntur. 5 are past their committed completion date and 0 are reported complete.
6
5
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Vijaya Durga Empire | Guntur | 9 Jul 2020 | 27 Oct 2021 | PAST DUE | D |
| Sri Vijaya Durga Estates | Guntur | 27 Oct 2020 | 6 Sep 2022 | PAST DUE | D |
| Park View Tower | Guntur | 8 Dec 2020 | 20 Feb 2023 | PAST DUE | D |
| Vijaya Durga Prasuna Tower | Guntur | 17 Nov 2021 | 13 Jan 2024 | PAST DUE | E |
| Rama Bliss | Guntur | 31 Dec 2021 | 15 Jul 2024 | PAST DUE | D |
| Sree Lalitha Vihaar | Guntur | 16 Feb 2026 | 16 Dec 2028 | REGISTERED | B |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Gona Sivanaga Babu have in Andhra Pradesh?
Gona Sivanaga Babu has 6 AP-RERA registered projects across Guntur. 5 are past their committed completion date and 0 are reported complete.
Does Gona Sivanaga Babu have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.