Doddapaneni Krishna Rao
Doddapaneni Krishna Rao has 4 AP-RERA registered projects across Vizianagaram. 3 are past their committed completion date and 0 are reported complete.
4
3
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Sri Krishna Nagar Ph-1 | Vizianagaram | 29 Jan 2021 | 18 Sep 2022 | STALLED | D |
| βSri Krishna Nagar Ph-2 | Vizianagaram | 29 Jan 2021 | 8 Jan 2023 | STALLED | D |
| Sidhartha Nagar | Vizianagaram | 7 Jul 2023 | 13 Mar 2026 | PAST DUE | C |
| Tandra Paparayudu Nagar | Vizianagaram | 29 Jun 2026 | 26 Mar 2029 | REGISTERED | B |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Doddapaneni Krishna Rao have in Andhra Pradesh?
Doddapaneni Krishna Rao has 4 AP-RERA registered projects across Vizianagaram. 3 are past their committed completion date and 0 are reported complete.
Does Doddapaneni Krishna Rao have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.