Dhanunjaya Builders
Dhanunjaya Builders has 5 AP-RERA registered projects across Visakhapatnam. 5 are past their committed completion date and 0 are reported complete.
5
5
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Sri Nilayam | Visakhapatnam | 30 Sep 2019 | 4 Sep 2020 | STALLED | C |
| Mahalakshmi Nilayam | Visakhapatnam | 12 Aug 2020 | 28 Aug 2022 | STALLED | C |
| Lakshmi Narasimha Residency | Visakhapatnam | 2 Mar 2021 | 7 Sep 2023 | STALLED | C |
| Arya Enclave | Visakhapatnam | 9 Mar 2022 | 19 Nov 2024 | PAST DUE | C |
| Varalakshmi Nilayam | Visakhapatnam | 14 Nov 2023 | 23 Jun 2026 | PAST DUE | B |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Dhanunjaya Builders have in Andhra Pradesh?
Dhanunjaya Builders has 5 AP-RERA registered projects across Visakhapatnam. 5 are past their committed completion date and 0 are reported complete.
Does Dhanunjaya Builders have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.