Devarasetti Suresh Babu
Devarasetti Suresh Babu has 7 AP-RERA registered projects across Guntur. 5 are past their committed completion date and 0 are reported complete.
7
5
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Lemon Tree Park Block-B | Guntur | 2 Dec 2021 | 21 Feb 2020 | PAST DUE | D |
| Lemon Tree Park Block-D | Guntur | 2 Dec 2021 | 21 Mar 2020 | PAST DUE | D |
| Lemon Tree Park Block-C | Guntur | 9 Jan 2022 | 2 May 2020 | PAST DUE | D |
| Lemon Tree Park- Block-A | Guntur | 2 Dec 2021 | 2 May 2020 | STALLED | D |
| Dndl Smart City | Guntur | 29 Mar 2019 | 10 Oct 2024 | PAST DUE | D |
| Dndl Smile City | Guntur | 31 Jul 2025 | 9 Jan 2028 | REGISTERED | B |
| Dndl Sunshine Park-1 | Guntur | 12 Mar 2024 | 20 Dec 2026 | REGISTERED | B |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Devarasetti Suresh Babu have in Andhra Pradesh?
Devarasetti Suresh Babu has 7 AP-RERA registered projects across Guntur. 5 are past their committed completion date and 0 are reported complete.
Does Devarasetti Suresh Babu have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.