Home/Andhra Pradesh/Builders/Chitturi Infra

Chitturi Infra

Chitturi Infra has 3 AP-RERA registered projects across East Godavari. 2 are past their committed completion date and 0 are reported complete.

3
2
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Chitturi's Metro Tower-B East Godavari 23 Jul 2021 20 Oct 2023 STALLED C
Chitturi's Metro Tower C East Godavari 27 Sep 2023 27 Sep 2025 PAST DUE B
Chitturi's Metro Tower-E East Godavari 28 Aug 2024 24 May 2027 REGISTERED A

Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.

How many RERA projects does Chitturi Infra have in Andhra Pradesh?

Chitturi Infra has 3 AP-RERA registered projects across East Godavari. 2 are past their committed completion date and 0 are reported complete.

Does Chitturi Infra have any RERA litigation in Andhra Pradesh?

No litigation is flagged on the AP-RERA record for their projects.