Battula Srilakshmi
Battula Srilakshmi has 6 AP-RERA registered projects across Guntur. 5 are past their committed completion date and 0 are reported complete.
6
5
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Harmony Homes | Guntur | 9 Apr 2019 | 31 Dec 2020 | STALLED | D |
| Tummeti Residency | Guntur | 26 Jan 2021 | 21 Oct 2023 | STALLED | D |
| Neeladri Nilayam | Guntur | 23 Jul 2021 | 8 Feb 2024 | STALLED | D |
| Bankmen Apartments | Guntur | 23 Sep 2021 | 3 Jul 2024 | STALLED | D |
| Brissa Residency | Guntur | 13 Jul 2023 | 16 Mar 2026 | PAST DUE | C |
| Mridini Residency | Guntur | 9 Dec 2024 | 2 Jan 2027 | REGISTERED | B |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Battula Srilakshmi have in Andhra Pradesh?
Battula Srilakshmi has 6 AP-RERA registered projects across Guntur. 5 are past their committed completion date and 0 are reported complete.
Does Battula Srilakshmi have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.