Home/Localities/Central Chennai/Prime Jeddy Residenza

Prime Jeddy Residenza

TN/29/Building/405/2023PAST COMMITTED DATE

Prime Jeddy Residenza is registered with TNRERA as TN/29/Building/405/2023 (Building registration, 2023). The promoter is 1) M/s. Prime Builders, Rep. by its Proprietor, Tmt. A.Fahameedha Banu and 2) Thiru. Arif Ali Jeddy. The RERA-committed completion date is 1 Jun 2024 — that date has now passed. Committed dates are legally binding under RERA.

20 Sep 2023
1 Jun 2024
8
0

Latest quarterly progress filing — March 2024

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 75% physical completion. Ask the builder for the current status and updated timeline before paying anything.

75%
75%

Stage, as filed: Block/Tower, Floor wise Completion

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Prime Jeddy Residenza” - Construction of Registration for Stilt Floor + 4 Floors Residential Building with 08 Dwelling Units at Old D.No.8/1, New D.No.23, Nageswara Iyer Road, Nungambakkam, Chennai – 600034 comprised in R.S.Nos.135/4 & 134/11, Block No.21 of Nungambakkam Village within the limit of Greater Chennai Corporation.

Approval: CMDA issued Planning Permission No. PP/NHRB/237/2021 in Letter No. PP/NHRB/C/182/2021, dated 11.08.2021. The Executive Engineer (T.P), Greater Chennai Corporation issued Building Permission No. CEBA/WDCN09/00283/2021, da

Status on register: Progress of Work as on March 2024

Builder track record: 1) M/s. Prime Builders, Rep. by its Proprietor, Tmt. A.Faham

1) M/s. Prime Builders, Rep. by its Proprietor, Tmt. A.Fahameedha Banu and 2) Thiru. Arif Ali Jeddy has 1 project on the TNRERA register since 2023, with no completion-date extensions on record.

Frequently asked

Is Prime Jeddy Residenza RERA registered?

Yes — registered with TNRERA as TN/29/Building/405/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Prime Jeddy Residenza be completed?

The RERA-committed completion date is 1 Jun 2024. No deadline extensions are on record.

Who is the builder of Prime Jeddy Residenza?

1) M/s. Prime Builders, Rep. by its Proprietor, Tmt. A.Fahameedha Banu and 2) Thiru. Arif Ali Jeddy.

← All Central Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →