TN/29/Building/0449/2020PAST COMMITTED DATE

Construction of Stilt Floor + 3 Floors of 4 dwelling units in each… is registered with TNRERA as TN/29/Building/0449/2020 (Building registration, 2020). The promoter is Tmt. P.Rukmani, Proprietor, M/s. Sree Sai Foundations. The RERA-committed completion date is 15 Sep 2022 — that date has now passed. Committed dates are legally binding under RERA.

4 Dec 2020
15 Sep 2022
12
0

About this registration

Construction of Stilt Floor + 3 Floors of 4 dwelling units in each Floors and by totalling 12 dwelling units at Plot Nos. 18, 19, R.E. Nagar, Okkiam Thoraipakkam, Chennai comprised in Old S.No.24/11A, New S.No.24/83 of Thoraipakkam Village, Sholinganallur Taluk, Chennai District.

Approval: Planning Permission issued by the Executive Engineer (T.P.), Greater Chennai Corporation vide Letter No. PPA/WDCN15/02065/2020, dated 16.06.2020 and the Building Permission issued by the Executive Engineer (T.P.), Greate

Builder track record: Tmt. P.Rukmani, Proprietor, M/s. Sree Sai Foundations

Tmt. P.Rukmani, Proprietor, M/s. Sree Sai Foundations has 1 project on the TNRERA register since 2020, with no completion-date extensions on record.

Frequently asked

Is Construction of Stilt Floor + 3 Floors of 4 dwelling units in each… RERA registered?

Yes — registered with TNRERA as TN/29/Building/0449/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Stilt Floor + 3 Floors of 4 dwelling units in each… be completed?

The RERA-committed completion date is 15 Sep 2022. No deadline extensions are on record.

Who is the builder of Construction of Stilt Floor + 3 Floors of 4 dwelling units in each…?

Tmt. P.Rukmani, Proprietor, M/s. Sree Sai Foundations.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.