Thiruchinnan Kuppam Phase-II

TN/29/Building/0417/2020PAST COMMITTED DATE

Thiruchinnan Kuppam Phase-II is registered with TNRERA as TN/29/Building/0417/2020 (Building registration, 2020). The promoter is The Executive Engineer, who has 117 projects on the TNRERA register. The RERA-committed completion date is 31 Dec 2024 — that date has now passed. Committed dates are legally binding under RERA.

17 Nov 2020
31 Dec 2024
0

Latest quarterly progress filing

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 98% physical completion. Ask the builder for the current status and updated timeline before paying anything.

98%
93%

Stage, as filed: Block/Tower, Floor wise

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Thiruchinnan Kuppam Phase-II” - Construction of Type–C, Block–C1, C2, C3 of Ground Floor + 4 Floors with 120 tenements in each Block and by totalling 360 tenements at Ennore Express way and Thiruchinnan Kuppam Main Road, Thiruchinnan Kuppam, Chennai comprised in S.Nos.194/1A, 1B, 1, 2, 3, 195/12, 197 & 198/1A, 2A, 2B, T.S.Nos.1, 20, 21, 22, 23, 24, Ward–J, Block No.12 of Thiruvottiyur Village, Greater Chennai Corporation, Chennai District.

Approval: Planning Permission issued by the Member-Secretary, CMDA, Chennai vide Letter No. PP/NHRB/N/254/2020, dated 24.07.2020 and the Building Permission issued by the Executive Engineer (T.P.), Greater Chennai Corporation vide

Status on register: Progress of Work as on September 2023

Builder track record: The Executive Engineer

The Executive Engineer has 117 projects on the TNRERA register since 2019, with no completion-date extensions on record. See the full record →

Frequently asked

Is Thiruchinnan Kuppam Phase-II RERA registered?

Yes — registered with TNRERA as TN/29/Building/0417/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Thiruchinnan Kuppam Phase-II be completed?

The RERA-committed completion date is 31 Dec 2024. No deadline extensions are on record.

Who is the builder of Thiruchinnan Kuppam Phase-II?

The Executive Engineer, with 117 projects on the TNRERA register and no completion-date extensions on record.

← All North Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.