Home/Localities/North Chennai/Lakeside 3

Lakeside 3

TN/29/Building/0401/2021REGISTERED

Lakeside 3 is registered with TNRERA as TN/29/Building/0401/2021 (Building registration, 2021). The promoter is M/s. Silver Sky Builders LLP, who has 5 projects on the TNRERA register. The RERA-committed completion date is 30 Nov 2026 (about 4 months away). Committed dates are legally binding under RERA.

3 Dec 2021
30 Nov 2026
430
0

Latest quarterly progress filing — DEC 2023

Stage, as filed: Block/Tower, Floor wise Block B Tiling completed. Block C Tiling completed. Block D Tiling completed. Block E Tiling is in progress.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Lakeside 3” - Construction of Group Development of High Rise Residential Cum Commercial Building in which Block No.A & B: Stilt Floor + 8 Floors with 88 Dwelling Units in each Block, Block No.C: Stilt Floor Part / Ground Floor Part (for Club House use) + 1st Floor (for Partly Residential & Partly Club House use) + 2nd Floor to 8th Floor with 78 Dwelling Units, Block No.D & E: Stilt Floor + 1st Floor to 8th Floor with 88 Dwelling Units in each Blocks, Totally 430 Dwelling Units and Block No.F (Commercial Block): Basement Floor + Ground Floor + 2 Floors abutting Ambattur – Puzhal Road, Puzhal, Chennai – 600066 comprised in Old S.No.461, S.No.461/1A1A as per Patta, New S.No.461/4

Approval: CMDA issued Planning Permission No. C/PP/MSB/50(A to I)/2021 in Letter No. C3(N)/0498/2019, dated 30.09.2021. Greater Chennai Corporation issued Building Permission No. CBEA/WDCN03/00328/2021, dated 03.11.2021

Status on register: Progress of Work as on March 2025

Builder track record: M/s. Silver Sky Builders LLP

M/s. Silver Sky Builders LLP has 5 projects on the TNRERA register since 2018, with no completion-date extensions on record. See the full record →

Frequently asked

Is Lakeside 3 RERA registered?

Yes — registered with TNRERA as TN/29/Building/0401/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Lakeside 3 be completed?

The RERA-committed completion date is 30 Nov 2026. No deadline extensions are on record.

Who is the builder of Lakeside 3?

M/s. Silver Sky Builders LLP, with 5 projects on the TNRERA register and no completion-date extensions on record.

← All North Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.