Casagrand Utopia

TN/29/Building/0240/2020PAST COMMITTED DATE

Casagrand Utopia is registered with TNRERA as TN/29/Building/0240/2020 (Building registration, 2020). The promoter is M/s. Casa Grande Smart Value Homes Private Limited, Devi Apartments. The RERA-committed completion date is 6 May 2023 — that date has now passed. Committed dates are legally binding under RERA.

24 Jul 2020
6 May 2023
673
0

Latest quarterly progress filing — December 2023

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 75% physical completion. Ask the builder for the current status and updated timeline before paying anything.

75%
75%

Stage, as filed: Block/Tower, Floor wise

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Casagrand Utopia” - Construction of Group development of 5 Blocks, Combined Basement Floor connecting Block No. 1, 2 & 3 and Combined Basement Floor connecting Block No. 4 & 5; Block-1 consisting of Combined Basement Floor + Ground Floor + 4 Floors (15.49m Height) with 43 Residential dwelling units, Indoor Games, Association Room at Ground Floor Level & Swimming Pool at 1st Floor Level; Block-2 consisting of Combined Basement Floor + Ground Floor + 4 Floors (15.49m Height) with 45 Residential dwelling units; Block-3 consisting of Combined Basement Floor + Ground Floor + 4 Floors (15.49m Height) with 312 Residential dwelling units; Block-4 consisting of Combined Basement Floor

Approval: CMDA issued Planning Permission No. B/NHRB/123–A1 to A30/2020, in Letter No. PP/ NHRB/S(B1)/1062/2019, dated 16.05.2020. Greater Chennai Corporation issued the Building Permission vide Letter No. CEBA/WDCN12/00166/2020,

Status on register: Progress of Work as on June 2025

Builder track record: M/s. Casa Grande Smart Value Homes Private Limited, Devi Apa

M/s. Casa Grande Smart Value Homes Private Limited, Devi Apartments has 1 project on the TNRERA register since 2020, with no completion-date extensions on record.

Frequently asked

Is Casagrand Utopia RERA registered?

Yes — registered with TNRERA as TN/29/Building/0240/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Casagrand Utopia be completed?

The RERA-committed completion date is 6 May 2023. No deadline extensions are on record.

Who is the builder of Casagrand Utopia?

M/s. Casa Grande Smart Value Homes Private Limited, Devi Apartments.

← All Porur Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.