VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Central Chennai/Crown Residences

Crown Residences

TN/29/Building/0184/2020PAST COMMITTED DATE

Crown Residences is registered with TNRERA as TN/29/Building/0184/2020 (Building registration, 2020). The promoter is 1) M/s. Baashyaam Constructions Pvt. Ltd.. The RERA-committed completion date is 27 Feb 2025 — that date has now passed. Committed dates are legally binding under RERA.

18 Jun 2020
27 Feb 2025
2,078
0

A quarterly progress filing exists for this project on the TNRERA register as a scanned document; we haven't machine-read it yet.

About this registration

Project Name: "Crown Residences" - Construction of Combined Double basement Floor for Tower 1 to 5, Common Stilt Floor cum Ground floor for Tower 1 to 5 with Tower – 1 & 2: 1st Floor to 27th Floor + 28th Floor (part) + 29th Floor (part) – Residential Tower with 973 dwelling units; Tower – 3: 1st floor to 26 floors + 27th floor (part) + 28th floor (part) – Residential Tower with 214 dwelling units; Tower – 4: 1st floor to 26 floors + 27th floor (part) + 28th floor (part) – Residential Tower with 420 dwelling units; Tower – 5: 1st Floor to 27th floor – Residential tower with 46 dwelling units; Block – 6: Triple Basement floor + Stilt floor + 1st floor with Amenities area & Parking area + 2nd f

Approval: Revised Planning Permission issued by the Member Secretary/CMDA/Chennai vide Letter No. C3(N)/589/2019 dated 28.02.2020 and the Building Permission issued by Executive Engineer(TP), Greater Chennai Corporation Vide Lette

Status on register: Progress of Work as on December 2025

Builder track record: 1) M/s. Baashyaam Constructions Pvt. Ltd.

1) M/s. Baashyaam Constructions Pvt. Ltd. has 1 project on the TNRERA register since 2020, with no completion-date extensions on record.

Frequently asked

Is Crown Residences RERA registered?

Yes — registered with TNRERA as TN/29/Building/0184/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Crown Residences be completed?

The RERA-committed completion date is 27 Feb 2025. No deadline extensions are on record.

Who is the builder of Crown Residences?

1) M/s. Baashyaam Constructions Pvt. Ltd..

← All Central Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.