VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/OMR Corridor/Kanya Chakra

Kanya Chakra

TN/29/Building/0052/2023PAST COMMITTED DATE

Kanya Chakra is registered with TNRERA as TN/29/Building/0052/2023 (Building registration, 2023). The promoter is M/s. Kanya Homes Pvt. Ltd., who has 3 projects on the TNRERA register. The RERA-committed completion date is 30 Dec 2024 — that date has now passed. Committed dates are legally binding under RERA.

24 Jan 2023
30 Dec 2024
12
0

Latest quarterly progress filing — September 2024

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 92% physical completion. Ask the builder for the current status and updated timeline before paying anything.

92%
92%

Stage, as filed: Block/Tower, Floor wise work to be completed

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Kanya Chakra” - Construction of Registration of Stilt + 3 Floors with 12 Dwelling Units (Ground Floor + Third Floor) comprised in S.Nos.237 & 238pt, Old S.No.18 & 19, New Survey No.18/3E1A2 & 19/1C1A3 of Kannan Street, Sri Balaji Nagar, Pallikaranai, Chennai District.

Approval: The Executive Engineer (T.P), Greater Chennai Corporation issued Planning Permission in P.P.No. PPA/WDCN14/09718/2022, dated 14.11.2022. The Executive Engineer (T.P), Greater Chennai Corporation issued the Building Permi

Status on register: Progress of Work as on September 2024

Builder track record: M/s. Kanya Homes Pvt. Ltd.

M/s. Kanya Homes Pvt. Ltd. has 3 projects on the TNRERA register since 2020, with no completion-date extensions on record. See the full record →

Frequently asked

Is Kanya Chakra RERA registered?

Yes — registered with TNRERA as TN/29/Building/0052/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Kanya Chakra be completed?

The RERA-committed completion date is 30 Dec 2024. No deadline extensions are on record.

Who is the builder of Kanya Chakra?

M/s. Kanya Homes Pvt. Ltd., with 3 projects on the TNRERA register and no completion-date extensions on record.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →