TN/29/Building/0047/2024PAST COMMITTED DATE

Pushkar is registered with TNRERA as TN/29/Building/0047/2024 (Building registration, 2024). The promoter is 1) Tmt. Amita Siromoni Nair, Flat-7 & 8. The RERA-committed completion date is 18 Mar 2025 — that date has now passed. Committed dates are legally binding under RERA.

12 Feb 2024
18 Mar 2025
10
0

Latest quarterly progress filing — March 2024

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 15% physical completion. Ask the builder for the current status and updated timeline before paying anything.

15%

Stage, as filed: each Block/Tower, Floor has been completed. Second Floor wise column concreting work is in progress

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Pushkar’s Phoenix” - Construction of Stilt Floor + 5 Floors Residential Building with 10 dwelling units at Plot No.2477, Old Door No.AJ-20, New Door No.2, 9th Main Road and 5th Street, Anna Nagar, Chennai – 600040 comprised in Old S.No.67 Part, 69 Part, 88 Part, T.S.No.11, Block No.1C of Naduvankarai Village, Aminjikarai Taluk, Chennai District.

Approval: Planning Permission issued by The Chief Planner / Area Plan Unit / CMDA / Chennai vide Letter No. CMDA/PP/NHRB/N/0270/2023, dated 02.11.2023. Building Permission issued by The Executive Engineer (T.P.) / Greater Chennai

Status on register: Progress of Work as on March 2024

Builder track record: 1) Tmt. Amita Siromoni Nair, Flat-7 & 8

1) Tmt. Amita Siromoni Nair, Flat-7 & 8 has 1 project on the TNRERA register since 2024, with no completion-date extensions on record.

Frequently asked

Is Pushkar RERA registered?

Yes — registered with TNRERA as TN/29/Building/0047/2024 in 2024. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Pushkar be completed?

The RERA-committed completion date is 18 Mar 2025. No deadline extensions are on record.

Who is the builder of Pushkar?

1) Tmt. Amita Siromoni Nair, Flat-7 & 8.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.