Home/Localities/Porur Belt/Construction of Stilt Floor + 3 Floors

Construction of Stilt Floor + 3 Floors

TN/29/Building/0021/2022PAST COMMITTED DATE

Construction of Stilt Floor + 3 Floors is registered with TNRERA as TN/29/Building/0021/2022 (Building registration, 2022). The promoter is 1) Thiru. S.Vijaya Mohan, who has 2 projects on the TNRERA register. The RERA-committed completion date is 31 May 2023 — that date has now passed. Committed dates are legally binding under RERA.

20 Jan 2022
31 May 2023
12
0

Latest quarterly progress filing — March 2023

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 80% physical completion. Ask the builder for the current status and updated timeline before paying anything.

80%

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

Carpet areas range from 194 to 782 sq.ft (median 480 sq.ft) across 11 units.

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of Stilt Floor + 3 Floors with 12 dwelling units comprised in Old S.No.76/7B, New S.No.76/7B1A of Mugalivakkam Village, Alandur Taluk, Chennai District.

Approval: Revised Planning Permission issued by The Executive Engineer (T.P.) / Greater Chennai Corporation / Chennai vide Letter No. PPA/WDCN12/07851/2021, dated 2/11/2021. Revised Building Permission issued by The Executive Engi

Status on register: Progress of Work as on March 2023

Builder track record: 1) Thiru. S.Vijaya Mohan

1) Thiru. S.Vijaya Mohan has 2 projects on the TNRERA register since 2022, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of Stilt Floor + 3 Floors RERA registered?

Yes — registered with TNRERA as TN/29/Building/0021/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Stilt Floor + 3 Floors be completed?

The RERA-committed completion date is 31 May 2023. No deadline extensions are on record.

Who is the builder of Construction of Stilt Floor + 3 Floors?

1) Thiru. S.Vijaya Mohan, with 2 projects on the TNRERA register and no completion-date extensions on record.

← All Porur Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.