MAYFLOWER EAST GATE PHASE II is registered with TNRERA as TN/11/Building/0226/2025 (Building registration, 2025). The promoter is M/s.MAYFLOWER ENTERPRISES PVT LTD (POA: N.RAMASUBRAMANIAN AND S.ARJUN). The RERA-committed completion date is 15 May 2030 (about 45 months away). Committed dates are legally binding under RERA.

28 Jun 2025
15 May 2030
26
0

From the detailed register filing

Not Yet Started
High Rise Building(HRB)
1809.20

Planning permission issued by DTCP COIMBATORE (No. 37/2025) on 23 Apr 2025, valid until 22 Apr 2033.

About this registration

Project Name: MAYFLOWER EAST GATE PHASE II Registration for Builder share of flat Nos: 1B, 1C, 2A, 2B, 3A, 3B, 3C, 4A, 4B, 4C, 5A, 5B, 6A, 6B, 7A, 7B, 8A, 8B, 8C, 9A, 9B, 9C (Total 22 Flats) of Basement Floor + Stilt Floor + 9 Floors residential building with 26 dwelling units comprised in Old S.No: 418/2pt, New TS No: 5/4 & 5/5, Block No: 07, Ward No: Z (26) of Villankurichi Village, Coimbatore North Taluk, Coimbatore District.

Approval: The Assistant Director, T&CP, Coimbatore District issued Planning Permission No: 37/2025 in Lr ROC No: SWP/BPA/0323360/2024 dated 23.04.2025. The Commissioner, Coimbatore Municipal Corporation issued buiding License No:

Builder track record: M/s.MAYFLOWER ENTERPRISES PVT LTD (POA: N.RAMASUBRAMANIAN AN

M/s.MAYFLOWER ENTERPRISES PVT LTD (POA: N.RAMASUBRAMANIAN AND S.ARJUN) has 1 project on the TNRERA register since 2025, with no completion-date extensions on record.

Frequently asked

Is MAYFLOWER EAST GATE PHASE II RERA registered?

Yes — registered with TNRERA as TN/11/Building/0226/2025 in 2025. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will MAYFLOWER EAST GATE PHASE II be completed?

The RERA-committed completion date is 15 May 2030. No deadline extensions are on record.

Who is the builder of MAYFLOWER EAST GATE PHASE II?

M/s.MAYFLOWER ENTERPRISES PVT LTD (POA: N.RAMASUBRAMANIAN AND S.ARJUN).

← All Coimbatore District projects and market data

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.