VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Coimbatore District/Silicon City

Silicon City

TN/11/Building/0209/2020COMPLETED

Silicon City is registered with TNRERA as TN/11/Building/0209/2020 (Building registration, 2020). The promoter is M/s. Town & City Developers, K G House, who has 13 projects on the TNRERA register. The RERA-committed completion date is 20 May 2025 — that date has now passed. Committed dates are legally binding under RERA.

10 Jul 2020
20 May 2025
205
0

About this registration

Project Name: “Silicon City” - Construction of Group development of Block A, B, C of Stilt Floor + 5 Floors residential building with 205 dwelling units comprised in S.No.77/2A1A in Visuvasapuram Saravanampatty Village, Coimbatore District.

Approval: The Member-Secretary, Coimbatore LPA issued Planning Permission No.81 “A to D”/2020 in Letter RC No.4644/2019/LPA-3, dated 21.05.2020. The Commissioner, Coimbatore Corporation, issued Building Permission No. BA/0390/2020

Status on register: Completed

Builder track record: M/s. Town & City Developers, K G House

M/s. Town & City Developers, K G House has 13 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Silicon City RERA registered?

Yes — registered with TNRERA as TN/11/Building/0209/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Silicon City be completed?

The RERA-committed completion date is 20 May 2025. No deadline extensions are on record.

Who is the builder of Silicon City?

M/s. Town & City Developers, K G House, with 13 projects on the TNRERA register and no completion-date extensions on record.

← All Coimbatore District projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.