Casagrand Linore is registered with TNRERA as TN/02/Building/035/2024 (Building registration, 2024). The promoter is 1) M/s. Casa Grande Civil Engineering Private Limited, Rep. by its Authorised Signatory, Thiru. R.Sumanth Krishna and 2) M/s. Arun Agencies, Rep. by its Partners, Thiru. AR.Meyyappan & Thiru. M.Kumarappan, NPL Devi. The RERA-committed completion date is 3 Apr 2027 (about 8 months away). Committed dates are legally binding under RERA.

7 Feb 2024
3 Apr 2027
275
0

Latest quarterly progress filing — December 2025

32%

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Casagrand Linore” - Construction of Registration of Basement Floor (Parking) + Ground Floor + 3 Floors + 4th Floor Part + 5th Floor Part (Height - 18.15m) Residential Building with 275 Dwelling Units with Swimming Pool, Kids Play Room, Association Room, Gym Indoor Games Room at Goparasanallur Main Road, Goparasanallur, Chennai comprised in Survey Nos.20/2, 22, 48/1A1, 48/1A2, 48/1A3, 48/1B1, 48/2A, 48/2B, 48/3, 49/1C1, 51/2, 52/3B2 of Goparasanallur Village within the limit of Poonamallee Panchayat Union.

Approval: CMDA issued Planning Permission No. OL-PP/NHRB/0001/2024 in Letter No. CMDA/PP/NHRB/C/0568/2023, dated 03.01.2024. The Commissioner, Poonamallee Panchayat Union approved and forwarded to Village Panchayat for Final appro

Status on register: Progress of Work as on December 2025

Builder track record: 1) M/s. Casa Grande Civil Engineering Private Limited, Rep.

1) M/s. Casa Grande Civil Engineering Private Limited, Rep. by its Authorised Signatory, Thiru. R.Sumanth Krishna and 2) M/s. Arun Agencies, Rep. by its Partners, Thiru. AR.Meyyappan & Thiru. M.Kumarappan, NPL Devi has 1 project on the TNRERA register since 2024, with no completion-date extensions on record.

Frequently asked

Is Casagrand Linore RERA registered?

Yes — registered with TNRERA as TN/02/Building/035/2024 in 2024. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Casagrand Linore be completed?

The RERA-committed completion date is 3 Apr 2027. No deadline extensions are on record.

Who is the builder of Casagrand Linore?

1) M/s. Casa Grande Civil Engineering Private Limited, Rep. by its Authorised Signatory, Thiru. R.Sumanth Krishna and 2) M/s. Arun Agencies, Rep. by its Partners, Thiru. AR.Meyyappan & Thiru. M.Kumarappan, NPL Devi.

← All Poonamallee Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.