VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Ambattur–Avadi Belt/Construction of Stilt floor + 3 floors + 4th floor part

Construction of Stilt floor + 3 floors + 4th floor part

TN/02/Building/0296/2018PAST COMMITTED DATE

Construction of Stilt floor + 3 floors + 4th floor part is registered with TNRERA as TN/02/Building/0296/2018 (Building registration, 2018). The promoter is M/s. Green Valley Shelters (P) Ltd., who has 7 projects on the TNRERA register. The RERA-committed completion date is 1 Aug 2020 — that date has now passed. Committed dates are legally binding under RERA.

19 Sep 2018
1 Aug 2020
22
0

A quarterly progress filing exists for this project on the TNRERA register as a scanned document; we haven't machine-read it yet.

About this registration

Construction of Stilt floor + 3 floors + 4th floor part residential building with 22 dwelling units at TNHB Block Nos.185, 186 & 187, Industrial Estate Road (Thirumangalam Road), Anna Nagar Western Extension, Chennai – 101, Old S.No.253/14 part, T.S.No.69/1, Block No.58, Ward – I of Padi Village, Ambattur Taluk, Tiruvallur District.

Approval: Approved by CMDA, Planning Permission No.B/Spl.Bldg./62 A to C/2018 in letter No.B3/2842/2016 dated 27.03.2018 and the Greater Chennai Corporation, Building Permission in letter No.CEBA/WDCN07/00148/2018 dated 25.05.2018

Status on register: Progress of Work as on December 2019

Builder track record: M/s. Green Valley Shelters (P) Ltd.

M/s. Green Valley Shelters (P) Ltd. has 7 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of Stilt floor + 3 floors + 4th floor part RERA registered?

Yes — registered with TNRERA as TN/02/Building/0296/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Stilt floor + 3 floors + 4th floor part be completed?

The RERA-committed completion date is 1 Aug 2020. No deadline extensions are on record.

Who is the builder of Construction of Stilt floor + 3 floors + 4th floor part?

M/s. Green Valley Shelters (P) Ltd., with 7 projects on the TNRERA register and no completion-date extensions on record.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.