VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Thiruvallur District/Construction of EWS Block 7 of Ground Floor + 18 floors

Construction of EWS Block 7 of Ground Floor + 18 floors

TN/02/Building/0258/2018PAST COMMITTED DATE

Construction of EWS Block 7 of Ground Floor + 18 floors is registered with TNRERA as TN/02/Building/0258/2018 (Building registration, 2018). The promoter is M/s. Prime Expat Infra Private Limited (previously M/s. Prime Expat Infra), who has 2 projects on the TNRERA register. The RERA-committed completion date is 30 Sep 2021 — that date has now passed. Committed dates are legally binding under RERA.

3 Aug 2018
30 Sep 2021
305
0

Latest quarterly progress filing — December 2023

Stage, as filed: Block/Tower,Floor wise 11th Slab – Completed

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

Carpet areas range from 447 to 636 sq.ft (median 466 sq.ft) across 31 units.

34% of units have a balcony on the filed area statement, typically around 158 sq.ft.

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of EWS Block 7 of Ground Floor + 18 floors residential building with 305 dwelling units-cum-commercial use at S.Nos.22/1A, 1B, 1C, 1D, 1E, 1F, 23/2, 3A, 3B, 3C, 4A, 4B, 5A1, 5A2, 5B, 5C, 6, 24/1, 2A, 2B, 4A1, 4A2, 4A3, 4A4, 4A5, 4B, 25/2, 26/1A, 2A, 2B, 2C of Peruncheri Village, Ponneri Taluk, Tiruvallur District.

Approval: Approved by the Commissioner, Town and Country Planning, Chennai, PP No.74/2018 in letter No.1475/2018/CP dated 09/04/2018, the Deputy Director, Town and Country Planning, Chengelpet letter No.2478/2017/FM2 dated 19/06/2

Status on register: Progress of Work as on December 2025

Builder track record: M/s. Prime Expat Infra Private Limited (previously M/s. Prim

M/s. Prime Expat Infra Private Limited (previously M/s. Prime Expat Infra) has 2 projects on the TNRERA register since 2018, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of EWS Block 7 of Ground Floor + 18 floors RERA registered?

Yes — registered with TNRERA as TN/02/Building/0258/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of EWS Block 7 of Ground Floor + 18 floors be completed?

The RERA-committed completion date is 30 Sep 2021. No deadline extensions are on record.

Who is the builder of Construction of EWS Block 7 of Ground Floor + 18 floors?

M/s. Prime Expat Infra Private Limited (previously M/s. Prime Expat Infra), with 2 projects on the TNRERA register and no completion-date extensions on record.

← All Thiruvallur District projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.