VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Thiruvallur District/VRX FETE

VRX FETE

TN/02/Building/0188/2022PAST COMMITTED DATE

VRX FETE is registered with TNRERA as TN/02/Building/0188/2022 (Building registration, 2022). The promoter is M/s. Vijay Raja Homes Pvt. Ltd.. The RERA-committed completion date is 15 Nov 2024 — that date has now passed. Committed dates are legally binding under RERA.

26 May 2022
15 Nov 2024
245
0

Latest quarterly progress filing

80%

Stage, as filed: each Block/Tower, 2. Internal Plastering toilet 75% Floor-wise Completed.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
1BHK162–48938
4BHK5861
2BHK197–47540
Studio196–43221

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Project Name: “VRX FETE” - Construction of Stilt Floor + 5 Floors residential building with 245 dwelling units (Block A – 80 + Block B – 165 dwelling units) and one Block – Gound + 2 Floors Association Room, Gym and Swimming Pool comprised in S.Nos.256/2A & 256/3B of Ponamallee Village, Tiruvallur District.

Approval: CMDA issued Planning Permission No. PP/NHRB/C/240/2021 in Letter No. PP/NHRB/C/240/2021, dated 07.12.2021. The Commissioner, Poonamallee Municipality issued Building Permission No. 010/CP/21-22/0003595, dated 25.03.2022

Status on register: Progress of Work as on December 2025

Builder track record: M/s. Vijay Raja Homes Pvt. Ltd.

M/s. Vijay Raja Homes Pvt. Ltd. has 1 project on the TNRERA register since 2022, with no completion-date extensions on record.

Frequently asked

Is VRX FETE RERA registered?

Yes — registered with TNRERA as TN/02/Building/0188/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will VRX FETE be completed?

The RERA-committed completion date is 15 Nov 2024. No deadline extensions are on record.

Who is the builder of VRX FETE?

M/s. Vijay Raja Homes Pvt. Ltd..

← All Thiruvallur District projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.