Home/Localities/North Chennai/Construction for 3 Blocks of Stilt floor + 4 floors for residential us

Construction for 3 Blocks of Stilt floor + 4 floors for residential us

TN/02/Building/0086/2018PAST COMMITTED DATE

Construction for 3 Blocks of Stilt floor + 4 floors for residential us is registered with TNRERA as TN/02/Building/0086/2018 (Building registration, 2018). The promoter is M/s. Rajarathnam Construction Pvt. Ltd., who has 5 projects on the TNRERA register. The RERA-committed completion date is 19 Feb 2023 — that date has now passed. Committed dates are legally binding under RERA.

13 Mar 2018
19 Feb 2023
94
0

Latest quarterly progress filing

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 85% physical completion. Ask the builder for the current status and updated timeline before paying anything.

85%
75%

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Construction for 3 Blocks of Stilt floor + 4 floors for residential use with total 94 dwelling units at S.No.1448/4A2, 4B1, 4B2 and 1449/4B2, T.S.No.14/1, 14/2, 15, 16 & 29/2, Block No.14 and T.S.No.121/2, Block No.7, Ward ‘D’ of Madhavaram Village, Perambur-Redhills Road, Kalpalayam, Greater Chennai Corporation, Tiruvallur District.

Approval: Approved by CMDA – PP No.B/Spl.Bldg/28A to F/2018 in Lr. No.B3/570/2015, dt.20.02.2018 and the Greater Chennai Corporation, Building Permission Lr.No.CEBA/WDCN03/00071/2018, dt.05.03.2018

Status on register: Progress of Work as on December 2019

Builder track record: M/s. Rajarathnam Construction Pvt. Ltd.

M/s. Rajarathnam Construction Pvt. Ltd. has 5 projects on the TNRERA register since 2018, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction for 3 Blocks of Stilt floor + 4 floors for residential us RERA registered?

Yes — registered with TNRERA as TN/02/Building/0086/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction for 3 Blocks of Stilt floor + 4 floors for residential us be completed?

The RERA-committed completion date is 19 Feb 2023. No deadline extensions are on record.

Who is the builder of Construction for 3 Blocks of Stilt floor + 4 floors for residential us?

M/s. Rajarathnam Construction Pvt. Ltd., with 5 projects on the TNRERA register and no completion-date extensions on record.

← All North Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.