VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Sriperumbudur–Oragadam/Sobha Blossom

Sobha Blossom

TN/01/Layout/0134/2019COMPLETED

Sobha Blossom is registered with TNRERA as TN/01/Layout/0134/2019 (Layout registration, 2019). The promoter is 1) M/s. KILAI BUILDERS Pvt. Ltd., Kothari Buildings. The RERA-committed completion date is 31 Dec 2021 — that date has now passed. Committed dates are legally binding under RERA.

20 Sep 2019
31 Dec 2021
0

Latest quarterly progress filing — JUNE 2022

100%

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Sobha Blossom” - Layout of House sites in S.nos.126/2, 127/1, 2A, 2B, 130/1, 2A, 139/1A, 1B & 140/1A2 of Erumaiyur Village, Sriperumbudur Taluk, Kancheepuram District.

Approval: Approved by the Principal Secretary/CMDA Egmore Chennai-8 vide Letter No.L1/6186/2019 dated 19.07.19. Approved by the Special Officer/Erumaiyur Panchayat/BDO(VP)/Kundrathur Panchayat Union vide Letter No.02/2019-2020 dat

Status on register: Completed

From the filed planning approval

CMDA
19 Jul 2019
2 mo
L1/6186/2019

Document cross-check: the reference number on the filed approval document matches the approval declared in this project's RERA registration.

Survey number(s) on the approval document: 126/2,127/1,2 — match these against your sale deed.

More CMDA-approved projects →

Read via OCR from the scanned approval document filed with TNRERA — verify against the source document before relying on it.

Builder track record: 1) M/s. KILAI BUILDERS Pvt. Ltd., Kothari Buildings

1) M/s. KILAI BUILDERS Pvt. Ltd., Kothari Buildings has 1 project on the TNRERA register since 2019, with no completion-date extensions on record.

Frequently asked

Is Sobha Blossom RERA registered?

Yes — registered with TNRERA as TN/01/Layout/0134/2019 in 2019. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Sobha Blossom be completed?

The RERA-committed completion date is 31 Dec 2021. No deadline extensions are on record.

Who is the builder of Sobha Blossom?

1) M/s. KILAI BUILDERS Pvt. Ltd., Kothari Buildings.

← All Sriperumbudur–Oragadam projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.