TN/01/Building/0150/2018COMPLETED

Construction of Combined Basement Floor + combined Stilt Floor + 13… is registered with TNRERA as TN/01/Building/0150/2018 (Building registration, 2018). The promoter is M/s. NAVIN HOUSING & PROPERTIES (P) LTD., Navin Triumph. The RERA-committed completion date is 1 Dec 2019 — that date has now passed. Committed dates are legally binding under RERA.

7 May 2018
1 Dec 2019
0

Latest quarterly progress filing

100%

Stage, as filed: a) Basement A1 Completed b) Stilt floor A1 Completed c) First Floor to Fourteenth A1 1. Structural work (Roof and Floor Wall) completed.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Construction of Combined Basement Floor + combined Stilt Floor + 13 Floors + 14th floor part, Block – A1, A2 and A6 combined basement floor + combined stilt floor + 4 floors (Swimming Pool at 4th floor) of Club House, Block in S.No.19/6A1, 19/6A2, 19/6A3, 19/6B1, 19/6B2, 20/2B, 20/3, 20/4A, 20/4B, 20/4C, 20/5A1, 20/5A2, 20/5B1, 20/5B2, 37/6A, 37/6B, 37/7, 37/8, 37/9, 364/1B2 and 365/1B1 of Vengaivasal Village, Tambaram Taluk, Kancheepuram District.

Approval: Approved by CMDA PP No.C/PP/MSB/33 A to J/2013 in letter No.C3/12498/2011 dated 28.6.2013, the President, Vengaivasal 1st Grade Panchayat, Building Permission letter No.116/2013 dated 23.8.2013 and CMDA, renewed PP No.C/

Status on register: Completed

Builder track record: M/s. NAVIN HOUSING & PROPERTIES (P) LTD., Navin Triumph

M/s. NAVIN HOUSING & PROPERTIES (P) LTD., Navin Triumph has 1 project on the TNRERA register since 2018, with no completion-date extensions on record.

Frequently asked

Is Construction of Combined Basement Floor + combined Stilt Floor + 13… RERA registered?

Yes — registered with TNRERA as TN/01/Building/0150/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Combined Basement Floor + combined Stilt Floor + 13… be completed?

The RERA-committed completion date is 1 Dec 2019. No deadline extensions are on record.

Who is the builder of Construction of Combined Basement Floor + combined Stilt Floor + 13…?

M/s. NAVIN HOUSING & PROPERTIES (P) LTD., Navin Triumph.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.