Construction of Stilt floor + 4 floors

TN/01/Building/0126/2018PAST COMMITTED DATE

Construction of Stilt floor + 4 floors is registered with TNRERA as TN/01/Building/0126/2018 (Building registration, 2018). The promoter is M/s. Casa Grande Vallam LLP. The RERA-committed completion date is 4 Jan 2020 — that date has now passed. Committed dates are legally binding under RERA.

17 Apr 2018
4 Jan 2020
0

Latest quarterly progress filing — June, 2023

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 70% physical completion. Ask the builder for the current status and updated timeline before paying anything.

70%
70%

Stage, as filed: Block/Tower, Floor wise

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
2BHK419124

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of Stilt floor + 4 floors residential building with 136 EWS dwelling units S.Nos.308/1, 308/2, 308/3, 309/1, 309/2A, 309/2B, 309/3, 309/4, 309/5, 309/8, 309/10, 309/11, 309/12A, 309/12B, 309/13, 309/14, 309/15A, 309/15B, 309/16A, 309/16B, 309/16C, 309/16D, 309/17, 309/18A, 309/18B, 309/19, 309/20, 309/21, 309/22, 310/4, 310/5, 310/6, 310/7, 310/8, 310/9, 310/10, 310/12, 311/1A, 311/1B, 311/1C, 311/1D, 311/1E, 311/1F, 311/2, 311/3, 311/4, 311/5A, 311/5B, 311/5C, 311/6, 311/7, 311/8, 311/9, 311/10, 311/11, 311/12, 312/4, 312/5, 312/6, 312/7A, 312/7B, 312/8, 312/9, 312/10B, 312/10C, 312/12, 312/13, 313/1, 313/2, 313/3, 313/4, 313/5, 313/6, 313/8A, 313/8B, 313/9A, 313/9B, 313/9C, 31

Approval: Approved by the Comissioner, T&CP, Chennai letter No.1185/2014/CP dated 10.2.2014, the D.D. (i/c) T&CP Chengalpet, P.P. No. 34 (A to R)/2014 in Letter No.6350/2013/CM3 dated 04.06.2014, the President, Vallakottai Panchay

Status on register: Progress of Work as on June 2023

Builder track record: M/s. Casa Grande Vallam LLP

M/s. Casa Grande Vallam LLP has 1 project on the TNRERA register since 2018, with no completion-date extensions on record.

Frequently asked

Is Construction of Stilt floor + 4 floors RERA registered?

Yes — registered with TNRERA as TN/01/Building/0126/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Stilt floor + 4 floors be completed?

The RERA-committed completion date is 4 Jan 2020. No deadline extensions are on record.

Who is the builder of Construction of Stilt floor + 4 floors?

M/s. Casa Grande Vallam LLP.

← All Sriperumbudur–Oragadam projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.