VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Sriperumbudur–Oragadam/Construction of Combined Basement Floor – Block – 10, Ground fl…

Construction of Combined Basement Floor – Block – 10, Ground fl…

TN/01/Building/0100/2018PAST COMMITTED DATE

Construction of Combined Basement Floor – Block – 10, Ground fl… is registered with TNRERA as TN/01/Building/0100/2018 (Building registration, 2018). The promoter is M/s. AMARPRAKASH DEVELOPERS (P) LTD., who has 13 projects on the TNRERA register. The RERA-committed completion date is 31 Dec 2021 — that date has now passed. Committed dates are legally binding under RERA.

26 Mar 2018
31 Dec 2021
95
0

A quarterly progress filing exists for this project on the TNRERA register as a scanned document; we haven't machine-read it yet.

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
2BHK599–68560
3BHK874–96728
4BHK1,2517

4% of units have a balcony on the filed area statement, typically around 303 sq.ft.

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of Combined Basement Floor – Block – 10, Ground floor + 6 floors residential building with 95 dwelling units at S.Nos.124/2, 228/2, 229/3, 230, 231/1, 231/2, 232/1B, 232/2, 233/1B, 233/2B, 241, 242/1A, 243/1, 243/2A, 243/2B, 244, 248/2A2 & 248/2A3A Thirumudivakkam Main Road, Thirumudivakkam Village, Sriperumbudur Taluk, Kancheepuram District.

Approval: Approved by CMDA PP No: C/PP/MSB/54 (S1 to S49) / 2015 in letter No.C3(S)/14609/2014 dated 30.12.2015 and the President / Executive Officer, Thirumudivakkam Panchayat Building permission letter No.1/2016-17 dated 1.6.201

Status on register: Progress of Work as on September 2019

Planning permission for this project was issued by CMDA (read from the approval document on the TNRERA register).

Builder track record: M/s. AMARPRAKASH DEVELOPERS (P) LTD.

M/s. AMARPRAKASH DEVELOPERS (P) LTD. has 13 projects on the TNRERA register since 2018, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of Combined Basement Floor – Block – 10, Ground fl… RERA registered?

Yes — registered with TNRERA as TN/01/Building/0100/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Combined Basement Floor – Block – 10, Ground fl… be completed?

The RERA-committed completion date is 31 Dec 2021. No deadline extensions are on record.

Who is the builder of Construction of Combined Basement Floor – Block – 10, Ground fl…?

M/s. AMARPRAKASH DEVELOPERS (P) LTD., with 13 projects on the TNRERA register and no completion-date extensions on record.

← All Sriperumbudur–Oragadam projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →