Construction of Block No.1 – Stilt floor + 4 floors

TN/01/Building/0091/2018PAST COMMITTED DATE

Construction of Block No.1 – Stilt floor + 4 floors is registered with TNRERA as TN/01/Building/0091/2018 (Building registration, 2018). The promoter is M/s. Arun Excello Realty Pvt. Ltd., Bhattad Towers, who has 31 projects on the TNRERA register. The RERA-committed completion date is 28 Feb 2025 — that date has now passed. Committed dates are legally binding under RERA.

16 Mar 2018
28 Feb 2025
92
0

Latest quarterly progress filing — 31st December 2023

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 55% physical completion. Ask the builder for the current status and updated timeline before paying anything.

55%
64%

Stage, as filed: Block/Tower, Floor wise &3 Completed, Block -2 Fourth Floor Roof Completed, Block -3 – Completed.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
2BHK447–53216

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of Block No.1 – Stilt floor + 4 floors with 80 dwelling units, Block – 2 – Stilt floor + 4 floors with 80 dwelling units, Block No.3 – Stilt floor + 4 floors with 92 dwelling units comprised in S.No.91/1, 2, 94, 95, 98/1, 2 of Nenmeil Village, Thirukazhukundram Taluk, Kancheepuram District.

Approval: Approved by Commissioner, DTCP, Chennai vide letter No.117/2018/BA2 dated 5.2.18 and approved by Deputy Director (i/c), Chengalpattu Region vide letter No.5455/CR3 dated 28.2.2018. Building permission issued by Special O

Status on register: Progress of Work as on June 2025

Planning permission for this project was issued by DTCP (read from the approval document on the TNRERA register).

Builder track record: M/s. Arun Excello Realty Pvt. Ltd., Bhattad Towers

M/s. Arun Excello Realty Pvt. Ltd., Bhattad Towers has 31 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of Block No.1 – Stilt floor + 4 floors RERA registered?

Yes — registered with TNRERA as TN/01/Building/0091/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Block No.1 – Stilt floor + 4 floors be completed?

The RERA-committed completion date is 28 Feb 2025. No deadline extensions are on record.

Who is the builder of Construction of Block No.1 – Stilt floor + 4 floors?

M/s. Arun Excello Realty Pvt. Ltd., Bhattad Towers, with 31 projects on the TNRERA register and no completion-date extensions on record.

← All Kancheepuram District projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.