VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/OMR Corridor/Anarghya

Anarghya

TN/01/Building/0076/2020PAST COMMITTED DATE

Anarghya is registered with TNRERA as TN/01/Building/0076/2020 (Building registration, 2020). The promoter is M/s. Jain Housing & Constructions Ltd., who has 10 projects on the TNRERA register. The RERA-committed completion date is 30 Sep 2025 — that date has now passed. Committed dates are legally binding under RERA.

20 Feb 2020
30 Sep 2025
0

Latest quarterly progress filing

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 93% physical completion. Ask the builder for the current status and updated timeline before paying anything.

93%

Stage, as filed: Block/Tower, Floor wise Terrace

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Anarghya” - Construction of Block A - Stilt + 15 Floors in which the promoter’s share of Flats – 1st Floor Flat Nos. 101 to 110, 2nd Floor Flat Nos. 203, 204, 205, 206 & 207, 3rd Floor Flat Nos. 301 to 310, 4th Floor Flat Nos. 404 & 405, 5th Floor Flat Nos. 503, 504, 505 & 508, 7th Floor Flat Nos. 704 to 708, 8th Floor Flat Nos. 801 to 810, 9th Floor Flat Nos. 903, 908 & 909, 10th Floor Flat Nos. 1001, 1002, 1005, 1006, 1007, 1009 & 1010, 12th Floor Flat Nos. 1201 to 1210, 13th Floor Flat Nos.1303 & 1308, 14th Floor Flat Nos. 1401 to 1410, 15th Floor Flat Nos. 1502, 1503, 1507, 1508 & 1509 comprised in S.No.65/1A, 1B, 669/8A, 8B, 9, 670/5, 6, 7 of Pallikaranai Village, MMRD Ro

Approval: Planning Permission issued by Member-Secretary/CMDA/Egmore/Chennai-8, Vide Letter No.C3(S)/7947/2018, dated 06.12.2019. Building permission issued by Executive Engineer(TP)/Greater Chennai Corporation Vide No.CEBA/WDCN14

Status on register: Progress of Work as on September 2025

Builder track record: M/s. Jain Housing & Constructions Ltd.

M/s. Jain Housing & Constructions Ltd. has 10 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Anarghya RERA registered?

Yes — registered with TNRERA as TN/01/Building/0076/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Anarghya be completed?

The RERA-committed completion date is 30 Sep 2025. No deadline extensions are on record.

Who is the builder of Anarghya?

M/s. Jain Housing & Constructions Ltd., with 10 projects on the TNRERA register and no completion-date extensions on record.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this project featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.