M/s. KCEE PROPERTIES PVT.LTD.

M/s. KCEE PROPERTIES PVT.LTD. has 6 projects on the TNRERA register since 2019 — 60 units/plots in total, concentrated in Central Chennai. 0 completion-deadline extensions are recorded across their projects, and 2 projects are past their committed completion dates on the register. All figures from TNRERA public records.

6
2019
60
0

Company & registration

The promoter is registered as a company, incorporated in 2014. Corporate Identity Number U45202TN2014PTC095456.

Read from the promoter's incorporation / firm-registration certificate filed with TNRERA (year derived from the Corporate Identity Number).

Builder Performance Dashboard

Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.

17%
0%
1
30 mo
100%

Marked completed: share of their 6 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 6 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record. Disclosure completeness: share of key filing fields (stage, building type, site extent, planning permission, units, completion date) present on the detailed register — sampled for 3 of 6 projects.

All TNRERA registrations by M/s. KCEE PROPERTIES PVT.LTD.

ProjectRERA No.LocalityYearCommitted byUnits
KCEE SREEKARAM TN/29/Building/0032/2025 Central Chennai 2025 4 Jun 2027 4
KCEE KAMALALAYAM TN/29/Building/0068/2025 Central Chennai 2025 31 May 2027 10
KCEE CHAITHANYAM RA/29/BLG/0267/2025 Central Chennai 2025 30 Dec 2027 8
KCEE SRINIVASAM RA/29/BLG/0341/2025 Central Chennai 2025 31 Dec 2030 10
KCEE AARADHYAM TN/29/Building/0360/2024 Central Chennai 2024 30 Jun 2026 20
Construction of Stilt floor + 4 floors TN/29/Building/047/2019 Central Chennai 2019 29 Aug 2019 8 DONE

How to read this record

Does M/s. KCEE PROPERTIES PVT.LTD. deliver on time?

No completion-deadline extensions are recorded across their 6 registered projects — a clean register on this measure.

Where does M/s. KCEE PROPERTIES PVT.LTD. build?

Their registrations concentrate in Central Chennai.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this builder featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.