K-RERA/PRJ/TVM/123/2022 REGISTERED BUYER LEVERAGE
Yes — K-RERA/PRJ/TVM/123/2022, registered 21 Jul 2022 with K-RERA. Committed completion: 31 Dec 2026. 31.3% of units are reported sold.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 90 | Within its committed completion date. |
| Progress vs elapsed time | 54 | Promoter-reported physical progress 45% · financial 75% |
| Document filings | n/a | No public document list for this project (component excluded from score) |
| Legal cleanliness | 100 | No case, complaint or order recorded on the register |
| Builder track record | 97 | Based on Malabar Developers Pvt Ltd's portfolio: past-due and litigation share across their K-RERA projects |
Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.
Registration record
| Field | Value |
|---|---|
| Builder | Malabar Developers Pvt Ltd |
| Type | Residential · villa |
| Location | Pidaram, Malayinkeezh, KATTAKADA, Thiruvananthapuram — 695571 |
| Registered on | 21 Jul 2022 |
| Committed completion | 31 Dec 2026 |
| Units | 16 total · 5 sold |
| Land extent | 4,503 sq.m |
| Last QPR | Q1 2026 (submitted 2 Jul 2026) |
| Official certificate | K-RERA registration certificate (PDF) |
Availability signal
Slow-moving for its age — buyers may have negotiating leverage here.
Is Misty Orchids RERA registered?
Yes — K-RERA/PRJ/TVM/123/2022, registered 21 Jul 2022 with K-RERA. Committed completion: 31 Dec 2026. 31.3% of units are reported sold.
Who is the builder of Misty Orchids?
Malabar Developers Pvt Ltd. See their full Kerala track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.