Yes — K-RERA/PRJ/TVM/051/2025, registered 7 May 2025 with K-RERA. Committed completion: 15 Nov 2031. 37.5% of units are reported sold.

A
37.5%
44%
15 Nov 2031

Health score components

ComponentScoreReading
Timeline adherence90Within its committed completion date.
Progress vs elapsed time100Promoter-reported physical progress 44% · financial 34%
Document filingsn/aNo public document list for this project (component excluded from score)
Legal cleanliness100No case, complaint or order recorded on the register
Builder track record100Based on Nikunjam Constructions Private Limited's portfolio: past-due and litigation share across their K-RERA projects

Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.

Registration record

FieldValue
BuilderNikunjam Constructions Private Limited
TypeResidential · apartment
LocationOpp. Mgm School, Attipra, Thiruvananthapuram, Thiruvananthapuram — 695583
Registered on7 May 2025
Committed completion15 Nov 2031
Units200 total · 75 sold
Land extent6,519 sq.m
Last QPRQ1 2026 (submitted 7 Jul 2026)
Official certificateK-RERA registration certificate (PDF)

Availability signal

37.5%

Sales absorption is in the normal range for the register.

Is Nikunjam The Summit RERA registered?

Yes — K-RERA/PRJ/TVM/051/2025, registered 7 May 2025 with K-RERA. Committed completion: 15 Nov 2031. 37.5% of units are reported sold.

Who is the builder of Nikunjam The Summit?

Nikunjam Constructions Private Limited. See their full Kerala track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.