VerifyRERAKerala · K-RERA
Home/Kerala/Thiruvananthapuram/Sowparnika Sandal Tower

Sowparnika Sandal Tower

K-RERA/PRJ/TVM/045/2022 COMPLETED

Yes — K-RERA/PRJ/TVM/045/2022, registered 22 Mar 2022 with K-RERA. Committed completion: 31 Oct 2024. 100% of units are reported sold.

B
100%
100%
31 Oct 2024

Health score components

ComponentScoreReading
Timeline adherence80Marked completed on the register.
Progress vs elapsed time100Promoter-reported physical progress 100% · financial 100%
Document filings701 document(s) filed publicly
Legal cleanliness50Case reported
Builder track record86Based on Sowparnika Projects & Infrasturcture Pvt Ltd's portfolio: past-due and litigation share across their K-RERA projects

Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.

Registration record

FieldValue
BuilderSowparnika Projects & Infrasturcture Pvt Ltd
TypeResidential · apartment
LocationCheruvakkal, Thiruvananthapuram, Thiruvananthapuram — 695017
Registered on22 Mar 2022
Committed completion31 Oct 2024
Units56 total · 56 sold
Land extent2,065 sq.m
Last QPRQ4 2023 (submitted 7 Apr 2024)
Official certificateK-RERA registration certificate (PDF)

Availability signal

100%

Sales absorption is in the normal range for the register.

Is Sowparnika Sandal Tower RERA registered?

Yes — K-RERA/PRJ/TVM/045/2022, registered 22 Mar 2022 with K-RERA. Committed completion: 31 Oct 2024. 100% of units are reported sold.

Who is the builder of Sowparnika Sandal Tower?

Sowparnika Projects & Infrasturcture Pvt Ltd. See their full Kerala track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.