Home/Kerala/Thiruvananthapuram/Heather Steps

Heather Steps

K-RERA/PRJ/TVM/041/2024 REGISTERED

Yes — K-RERA/PRJ/TVM/041/2024, registered 16 Feb 2024 with K-RERA. Committed completion: 15 Dec 2028. 77.8% of units are reported sold.

A
77.8%
26%
15 Dec 2028

Health score components

ComponentScoreReading
Timeline adherence90Within its committed completion date.
Progress vs elapsed time77Promoter-reported physical progress 26% · financial 38%
Document filingsn/aNo public document list for this project (component excluded from score)
Legal cleanliness100No case, complaint or order recorded on the register
Builder track record100Based on Heather Homes Private Limited's portfolio: past-due and litigation share across their K-RERA projects

Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.

Registration record

FieldValue
BuilderHeather Homes Private Limited
TypeResidential · apartment
LocationNalanchira, Kudappanakunnu, Thiruvananthapuram, Thiruvananthapuram — 695015
Registered on16 Feb 2024
Committed completion15 Dec 2028
Units99 total · 77 sold
Land extent3,893 sq.m
Last QPRQ1 2026 (submitted 6 Jul 2026)
Official certificateK-RERA registration certificate (PDF)

Availability signal

77.8%

Sales absorption is in the normal range for the register.

Is Heather Steps RERA registered?

Yes — K-RERA/PRJ/TVM/041/2024, registered 16 Feb 2024 with K-RERA. Committed completion: 15 Dec 2028. 77.8% of units are reported sold.

Who is the builder of Heather Steps?

Heather Homes Private Limited. See their full Kerala track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.