VerifyRERAKerala · K-RERA
Home/Kerala/Thiruvananthapuram/Sparrow Paradisia

Sparrow Paradisia

K-RERA/PRJ/TVM/038/2022 PAST DUE

Yes — K-RERA/PRJ/TVM/038/2022, registered 10 Mar 2022 with K-RERA. Committed completion: 28 Feb 2023. 87.5% of units are reported sold.

D
87.5%
97%
28 Feb 2023

Health score components

ComponentScoreReading
Timeline adherence15Overdue 3.4 yrs vs committed date; no extension on file
Progress vs elapsed timen/aPromoter-reported physical progress 97% · financial 90%
Document filingsn/aNo public document list for this project (component excluded from score)
Legal cleanliness100No case, complaint or order recorded on the register
Builder track record30Based on Sparrow Construction Management And Consultancy's portfolio: past-due and litigation share across their K-RERA projects

Confidence: partial — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.

Registration record

FieldValue
BuilderSparrow Construction Management And Consultancy
TypeResidential · apartment
LocationAmabalamukku, Kudappanakunnu, Thiruvananthapuram, Thiruvananthapuram — 695005
Registered on10 Mar 2022
Committed completion28 Feb 2023
Units16 total · 14 sold
Land extent953 sq.m
Last QPRQ1 2025 (submitted 9 Jul 2025)
Official certificateK-RERA registration certificate (PDF)

Availability signal

87.5%

Sales absorption is in the normal range for the register.

Is Sparrow Paradisia RERA registered?

Yes — K-RERA/PRJ/TVM/038/2022, registered 10 Mar 2022 with K-RERA. Committed completion: 28 Feb 2023. 87.5% of units are reported sold.

Who is the builder of Sparrow Paradisia?

Sparrow Construction Management And Consultancy. See their full Kerala track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.