Yes — K-RERA/PRJ/TSR/228/2024, registered 18 Nov 2024 with K-RERA. Committed completion: 31 Dec 2026.
B
—
0%
31 Dec 2026
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 90 | Within its committed completion date. |
| Progress vs elapsed time | 19 | Promoter-reported physical progress 0% · financial 0% |
| Document filings | n/a | No public document list for this project (component excluded from score) |
| Legal cleanliness | 100 | No case, complaint or order recorded on the register |
| Builder track record | 100 | Based on V N Developers's portfolio: past-due and litigation share across their K-RERA projects |
Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.
Registration record
| Field | Value |
|---|---|
| Builder | V N Developers |
| Type | Plotted · plots |
| Location | Chembukavu, Thrissur, Chembukavu, Thrissur, Thrissur — 680002 |
| Registered on | 18 Nov 2024 |
| Committed completion | 31 Dec 2026 |
| Units | 16 plots · 3 booked |
| Land extent | 4,117 sq.m |
| Last QPR | Q1 2026 (submitted 7 Jul 2026) |
| Official certificate | K-RERA registration certificate (PDF) |
Is Vnd Central Avenue RERA registered?
Yes — K-RERA/PRJ/TSR/228/2024, registered 18 Nov 2024 with K-RERA. Committed completion: 31 Dec 2026.
Who is the builder of Vnd Central Avenue?
V N Developers. See their full Kerala track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.