Yes — K-RERA/PRJ/KKD/012/2025, registered 20 Jan 2025 with K-RERA. Committed completion: 1 Jan 2029. 63.4% of units are reported sold.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 90 | Within its committed completion date. |
| Progress vs elapsed time | 96 | Promoter-reported physical progress 35% · financial 20% |
| Document filings | n/a | No public document list for this project (component excluded from score) |
| Legal cleanliness | 100 | No case, complaint or order recorded on the register |
| Builder track record | 100 | Based on Prisunic Builders Pvt Ltd's portfolio: past-due and litigation share across their K-RERA projects |
Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.
Registration record
| Field | Value |
|---|---|
| Builder | Prisunic Builders Pvt Ltd |
| Type | Residential · apartment |
| Location | Ummalathoor, Nellikode, Kozhikode, Kozhikode — 673008 |
| Registered on | 20 Jan 2025 |
| Committed completion | 1 Jan 2029 |
| Units | 41 total · 26 sold |
| Land extent | 1,642 sq.m |
| Last QPR | Q1 2026 (submitted 8 Jul 2026) |
| Official certificate | K-RERA registration certificate (PDF) |
Availability signal
Sales absorption is in the normal range for the register.
Is Cyberspace RERA registered?
Yes — K-RERA/PRJ/KKD/012/2025, registered 20 Jan 2025 with K-RERA. Committed completion: 1 Jan 2029. 63.4% of units are reported sold.
Who is the builder of Cyberspace?
Prisunic Builders Pvt Ltd. See their full Kerala track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.