Arya Bhangy Centara
K-RERA/PRJ/ERN/210/2022 PAST DUE
Yes — K-RERA/PRJ/ERN/210/2022, registered 20 Dec 2022 with K-RERA. Committed completion: 30 Nov 2025. 46.9% of units are reported sold.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 39 | Overdue 0.7 yrs vs committed date; no extension on file |
| Progress vs elapsed time | 100 | Promoter-reported physical progress 100% · financial 100% |
| Document filings | n/a | No public document list for this project (component excluded from score) |
| Legal cleanliness | 100 | No case, complaint or order recorded on the register |
| Builder track record | 65 | Based on Arya Bhangy Builders Pvt Ltd's portfolio: past-due and litigation share across their K-RERA projects |
Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.
Registration record
| Field | Value |
|---|---|
| Builder | Arya Bhangy Builders Pvt Ltd |
| Type | Mixed · mixed |
| Location | Opposite Silver Sand Isaland, Poonithura, Kanayannur, Ernakulam — 682019 |
| Registered on | 20 Dec 2022 |
| Committed completion | 30 Nov 2025 |
| Units | 32 total · 15 sold |
| Land extent | 2,001 sq.m |
| Last QPR | Q2 2025 (submitted 5 Oct 2025) |
| Official certificate | K-RERA registration certificate (PDF) |
Availability signal
Sales absorption is in the normal range for the register.
Is Arya Bhangy Centara RERA registered?
Yes — K-RERA/PRJ/ERN/210/2022, registered 20 Dec 2022 with K-RERA. Committed completion: 30 Nov 2025. 46.9% of units are reported sold.
Who is the builder of Arya Bhangy Centara?
Arya Bhangy Builders Pvt Ltd. See their full Kerala track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.