Riziere Meadows
K-RERA/PRJ/ERN/128/2025 PAST DUE
Yes — K-RERA/PRJ/ERN/128/2025, registered 22 Sep 2025 with K-RERA. Committed completion: 30 Jun 2026.
D
—
35%
30 Jun 2026
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 53 | Overdue 0.1 yrs vs committed date; no extension on file |
| Progress vs elapsed time | 35 | Promoter-reported physical progress 35% · financial 43% |
| Document filings | n/a | No public document list for this project (component excluded from score) |
| Legal cleanliness | 100 | No case, complaint or order recorded on the register |
| Builder track record | 30 | Based on Jose Antony's portfolio: past-due and litigation share across their K-RERA projects |
Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.
Registration record
| Field | Value |
|---|---|
| Builder | Jose Antony |
| Type | Plotted · plots |
| Location | Kunnathunad, Kunnathunad, Ernakulam — 683565 |
| Registered on | 22 Sep 2025 |
| Committed completion | 30 Jun 2026 |
| Units | 7 plots · 0 booked |
| Land extent | 2,740 sq.m |
| Last QPR | Q3 2025 (submitted 9 Jan 2026) |
| Official certificate | K-RERA registration certificate (PDF) |
Is Riziere Meadows RERA registered?
Yes — K-RERA/PRJ/ERN/128/2025, registered 22 Sep 2025 with K-RERA. Committed completion: 30 Jun 2026.
Who is the builder of Riziere Meadows?
Jose Antony. See their full Kerala track record on this site.