K-RERA/PRJ/ERN/098/2023 REGISTERED

Yes — K-RERA/PRJ/ERN/098/2023, registered 2 Jun 2023 with K-RERA. Committed completion: 26 Jan 2028.

A
100%
26 Jan 2028

Health score components

ComponentScoreReading
Timeline adherence90Within its committed completion date.
Progress vs elapsed time100Promoter-reported physical progress 100% · financial 100%
Document filingsn/aNo public document list for this project (component excluded from score)
Legal cleanliness100No case, complaint or order recorded on the register
Builder track record100Based on Meena Paul Alias Mobi's portfolio: past-due and litigation share across their K-RERA projects

Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.

Registration record

FieldValue
BuilderMeena Paul Alias Mobi
TypePlotted · plots
LocationKollappaddy, Vadavukode, Kunnathunad, Ernakulam — 682310
Registered on2 Jun 2023
Committed completion26 Jan 2028
Units31 plots · 31 booked
Land extent12,210 sq.m
Last QPRQ2 2025 (submitted 7 Oct 2025)
Official certificateK-RERA registration certificate (PDF)

Is Meena Paul Alias Meena Mobi RERA registered?

Yes — K-RERA/PRJ/ERN/098/2023, registered 2 Jun 2023 with K-RERA. Committed completion: 26 Jan 2028.

Who is the builder of Meena Paul Alias Meena Mobi?

Meena Paul Alias Mobi. See their full Kerala track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.