Royale Courtyard
K-RERA/PRJ/ERN/060/2024 PAST DUE
Yes — K-RERA/PRJ/ERN/060/2024, registered 12 Mar 2024 with K-RERA. Committed completion: 24 Nov 2025. 71.7% of units are reported sold.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 39 | Overdue 0.7 yrs vs committed date; no extension on file |
| Progress vs elapsed time | n/a | Promoter-reported physical progress 98% · financial 0% |
| Document filings | n/a | No public document list for this project (component excluded from score) |
| Legal cleanliness | 100 | No case, complaint or order recorded on the register |
| Builder track record | 15 | Based on Motif Builders And Developers Pvt Ltd's portfolio: past-due and litigation share across their K-RERA projects |
Confidence: partial — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.
Registration record
| Field | Value |
|---|---|
| Builder | Motif Builders And Developers Pvt Ltd |
| Type | Residential · apartment |
| Location | Vadacode, Thrikkakara North, Kanayannur, Ernakulam — 682021 |
| Registered on | 12 Mar 2024 |
| Committed completion | 24 Nov 2025 |
| Units | 53 total · 38 sold |
| Land extent | 3,030 sq.m |
| Last QPR | Q1 2026 (submitted 3 Jul 2026) |
| Official certificate | K-RERA registration certificate (PDF) |
Availability signal
Sales absorption is in the normal range for the register.
Is Royale Courtyard RERA registered?
Yes — K-RERA/PRJ/ERN/060/2024, registered 12 Mar 2024 with K-RERA. Committed completion: 24 Nov 2025. 71.7% of units are reported sold.
Who is the builder of Royale Courtyard?
Motif Builders And Developers Pvt Ltd. See their full Kerala track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.