K-RERA/PRJ/135/2021 STALLED BUYER LEVERAGE
Yes — K-RERA/PRJ/135/2021, registered 16 Aug 2021 with K-RERA. Committed completion: 31 Dec 2024. 0% of units are reported sold.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 10 | Overdue 1.6 yrs vs committed date; no extension on file |
| Progress vs elapsed time | 0 | Promoter-reported physical progress 0% · financial 10% |
| Document filings | n/a | No public document list for this project (component excluded from score) |
| Legal cleanliness | 100 | No case, complaint or order recorded on the register |
| Builder track record | 30 | Based on Apstone Infrastructure Pvt Ltd's portfolio: past-due and litigation share across their K-RERA projects |
Confidence: full — components without register data are excluded and the rest reweighted. Derived from public K-RERA records as of 2026-07-25; always verify with rera.kerala.gov.in before transacting.
Registration record
| Field | Value |
|---|---|
| Builder | Apstone Infrastructure Pvt Ltd |
| Type | Residential · villa |
| Location | Chengannur, Chengannur, Alappuzha — 689121 |
| Registered on | 16 Aug 2021 |
| Committed completion | 31 Dec 2024 |
| Units | 15 total · 0 sold |
| Land extent | 4,485 sq.m |
| Last QPR | — |
| Official certificate | K-RERA registration certificate (PDF) |
Availability signal
Slow-moving for its age — buyers may have negotiating leverage here.
Is Camelot RERA registered?
Yes — K-RERA/PRJ/135/2021, registered 16 Aug 2021 with K-RERA. Committed completion: 31 Dec 2024. 0% of units are reported sold.
Who is the builder of Camelot?
Apstone Infrastructure Pvt Ltd. See their full Kerala track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.